Project Schedule

Revitalization Activity Date HUD Timeliness Requirement
Developer procured February 15, 2006  
Submit HOPE VI Grant Application July 10, 2006  
HOPE VI Grant Award September 15, 2006 Date provided by HUD*
HOPE VI Grant Agreement execution November 15, 2006  
Begin case management HUD Request for Supplemental Submissions December 15, 2006 Start within 30 days of Grant Agreement execution
Submit CSS work plan to HUD February 15, 2007 Due within 90 days of Grant Agreement execution
Submit Supplemental Submissions to HUD March 15, 2007 Due within 90 days from the date of HUD's written request
HUD approval of Supplemental Submissions April 15, 2007  
PHASE I
FHA Loan/HOPE VI Rental (Regent I)
Finalize purchase of site per option November 15, 2006  
Complete Zoning Approval November 15, 2006  
Submit MF Proposal/Term Sheet to HUD July 10, 2006 Due within 12 months of Grant Award (September 15, 2007)
MF closing June 1, 2007 Due within 15 months of Grant Award (December 15, 2007)
Construction start June 1, 2007 Start within 12 months of HUD approval of Supplemental Submission (April 15, 2008) - not to exceed 18 months from Grant Agreement execution (May 15, 2007)
Construction completion July 1, 2008  
Lease-up complete November 1, 2008  
PHASE II
Market Rate/HOPE VI Homeownership (Regent I)
Finalize purchase of site per option November 15, 2006  
Complete Zoning Approval November 15, 2006  
Submit Homeownership Plan to HUD January 31, 2008  
Begin Homeownership
Pre-sales
April 1, 2008  
Construction start July 1, 2008  
Construction completion October 31, 2010  
PHASE III
FHA Loan/HOPE VI Rental (Pointe North)
Relocation Plan complete July 1, 2006  
Begin Resident Relocation June 1, 2008  
Submit MF Proposal/Term Sheet to HUD December 1, 2008  
Complete Resident Relocation November 1, 2008  
MF closing March 1, 2009  
Construction start March 1, 2009  
Construction completion April 1, 2010 Due within 48 months of HUD Approval of Supplemental Submission (April 15, 2011) - not to exceed 54 months from Grant Agreement Execution (April 15, 2011)
Lease-up complete October 1, 2010  

* Based on date provided by HUD on page 18498 of the NOFA